Revamping LPG Storage
Bringing the pipes and tanks of the NIORT LPG storage site up to PPRT standards.
Realization of the studies, prefabrication, assembly and management of site and subcontractors.
Identity card
Sector
Gas
Location
Niort (79)
Type of project
Prefabrication / Assembly
Delivered on
September 2018
Revamping LPG Storage
Manufacture and installation of 10 LPG Lines :
- 600 meters of piping DN100 and DN80
- Piping subject to PED II and III
- 200 meters of piping to collect the 45 safety valves.
- Installation of 150 meters of DN20 piping and of a VOC recovery station and loading arm purges.
- Modification and requalification work on a 100M3 LPG tank and replacement of its pumping system.
- Removal, modification and addition of tappings on the tank.
Realization of the requalification test. - Réalisation de l’épreuve de requalification.
- Carrying out the anti-corrosion maintenance of the tank.
- Replacement of 3 LPG pumps and suction and discharge piping.